Produciton plant, Horní Suchá

Construction of a production plant in the village of Horní Suchá with our partner company AKM STAVBY a.s..Investor is a company Magna Energy Storage a.s.. The contract is now being realized.

More photos
Administrative building, Prague

Reconstruction and reduction of the energy demands of the Printer building of the Ministry of the Interior of the Czech republic. The contract is now being realized

More photos
Primary school, Kostelec nad Černými lesy

Complete reconstruction of the Primary school in the town of Kostelec nad Černými lesy. The contract is now being realized.

More photos
Apartment building, Prague 2 - Jugoslávská

Complete reconstruction of an apartment building in Prague 2. The contract is now being realized.

More photos
Apartment building, Prague 2 - Vocelova

Complete reconstruction of an apartment building in Prague 2. The contract is now being realized.

More photos
Apartmemts building, Klíčany

Construction of 120 apartments in the village of Klíčany. The contract is now being realized.

More photos
Family Houses, Prague Chuchle

Construction of a 4 double-houses in Prague Chuchle. Investor is a company Darmar Property, s.r.o. The contract is now being realized.

More photos
Production plant, Kostelec nad Černými lesy

Construction of a production plant for the company EUROSUn a.s. in the town of Kostelec nad Černými lesy. The contract was realized in the year 2017 - 2018.

More photos
Administrative building, Nové Město nad Metují

Reconstruction and reduction of the energy demands of administrative building for the company ALUFRONT s.r.o. in the town of Nové Město nad Metují. The contract was realized in the year 2017 - 2018.

More photos
Gymnasium building, Ohrobec

Construction of the gymnasium building in the village of Ohrobec. The contract is now being realized

More photos
Family Houses, Prague Štěrboholy

Construction of a 13 family houses in Prague Štěrboholy. Investor is a company Euro Development Prague. The contract is now being realized.

More photos
Family Houses, Prague Jahodnice

Construction of a 7 family houses in Prague Jahodnice. Investor is a company Euro Development Prague. The contract is now being realized.

More photos
Firehouse, Ostředek

Construction of firehouse and reconstruction of the gymnasium building in Ostředek. The contract was realized in the year 2017 - 2018.

More photos
Municipal Authority building, Lány

A reduction of the energy demands of the Municipal Authority building in Lány. The contract was realized in the year 2017.

More photos
Railroad building, Prague Dejvice

Reconstruction of a railroad building in Prague Dejvice.The contract was realized in the year 2017.

More photos
Railroad building, Kutná Hora

Reconstruction of a railroad building in the town of Kutná Hora. The contract was realized in the year 2017.

More photos
Secondary school, Prague 4

Reconstruction and insulation of flat roof of a secondary technical and vocational school in Prague 4. The contract was realized in the year 2017.

More photos
Railroad building, Kostomlaty nad Labem

Reconstruction of a railroad building in the town of Kostomlaty nad Labem.The contract was realized in the year 2016 - 2017.

More photos
BestDrive branches, Praha, Plzeň, Ostrava

Reconstruction of the BestDrive branches in Prague, Plzen and Ostrava. The contract was realized during the period of May to June 2016.

More photos
Family house Prague Spořilov

Complete reconstruction and insulation of a family house in Prague - Spořilov. The contract was realized in the year 2016.

More photos
Administrative building, Prague 4

A reduction of the energy demands of administrative building of the company Zakládání Group a.s. in Prague 4 – Kunratice. The contract was realized in the year 2016.

More photos
Family house, Stříbrná Skalice

Construction of a family house in the village of Stříbrná Skalice. The contract was realized in the year 2016.

More photos
Secondary school, Prague 4

Reconstruction of a secondary technical and vocational school in Prague 4. The contract was realized in the year 2016.

More photos
Family house, Benešov

Reconstruction and insulation of a family house in the town of Benešov. The contract was realized during the period of March to April 2016.

More photos
Car showroom, Průhonice

Reconstruction of interior automobile manufacturer of the company Toyota Tsuscho in Prague. The contract was realized in the year 2016.

More photos
Gymnasium building, Heřmanův Městec

A reduction of the energy demands of the historical gymnasium building in the town of Heřmanův Městec. The contract was realized during the period of June to November 2015.

More photos
Primary school, Uhlířské Janovice

A reduction of the energy demands of the primary school in the town of Uhlířské Janovice. The contract was realized during the period of April to November 2015.

More photos
Production hall, Boskovice

Extension of a production hall for a leading plastic part manufacturer, the company JVP Praha, with production being located in the village of Žďárná. The contract was realized during the period of June to August 2015.

More photos
Health centre building, Ondřejov

A reduction of the energy demands of the health centre building in the village of Ondřejov. The contract was realized during the period of September to November 2015.

More photos
Municipal Authority building Ostředek

A reduction of the energy demands of the Municipal Authority building in Ostředek. The contract was realized from April to September 2015.

More photos
Car showroom, Průhonice

Construction of a car showroom and supporting wall for a world-famous automobile manufacturer, the company Toyota Tsuscho Praha. The construction work took place in the year 2014.

More photos
House of doctors, Velké Popovice

A reduction of the energy demands of the House of doctors in the town of Velké Popovice. The contract was realized during the period of September to November 2014.

More photos
Gymnasium building, Kostelec nad Černými lesy

A reduction of the energy demands of the gymnasium building in the town of Kostelec nad Černými lesy. The contract was realized during the period of August to November 2014.

More photos
Historical building, Prague 8 Karlín

Complete reconstruction, and project and engineering activity, for the owner of a historical building in Karlín in Prague. The contract was realized from May 2013 to April 2014.

More photos
Production plant, Boskovice

The reconstruction, modernization and expansion of a factory, including delivery of machines, for a leading plastic part manufacturer, the company JVP Praha, with production being located in the village of Žďárná. All work was carried out in the year 2013.

More photos
Apartment building, Prague 9

Reconstruction and insulation of an apartment building in Prague 9. The contract was realized during the period of February to November 2012.

More photos
Production plant, Ondřejov

Construction and engineering activity of a production plant for the company Bémaci, specializing in chimney components and systems. The construction took place from February to November 2013.

More photos
Family house, Ondřejov

Complete reconstruction and insulation of a family house in the village of Ondřejov. The contract was realized in the year 2014.

More photos
Primary school, Prague 13

Extension of the pavilion of professor O. Chlup Primary School in Prague 13. The ABP team ensured the execution of Technical Investor Supervision and the work of the OSH Co-ordinator. The contract was realized during the period of July to December 2016

More photos
High school, Benesov

A reduction of the energy demands of the Integrated Technical High School building complex in the town of Benešov. The ABP team ensured the execution of Technical Investor Supervision and the work of the OSH Co-ordinator. The contract was realized during the period of March to November 2015.

More photos
Gabion wall, Zbraslavice

Construction of a supporting gabion wall in the town of Zbraslavice. The ABP team performed Technical Investor Supervision. The contract was realized in the year 2014.

More photos
Pass, Keblov

Construction of a pass behind the village of Keblov. The ABP team performed Technical Investor Supervision. The contract was realized in the year 2014.

More photos
Polyclinic building, Prague 13

Complete reconstruction and insulation of Hostinského polyclinic building in Prague 13. ABP arranged the execution of Technical Investor Supervision. The contract was realized in the year 2014.

More photos
Health centre, Prague 13

Complete reconstruction and insulation of Seydlerova health centre in Prague 13. ABP realized the execution of Technical Investor Supervision, and the work of the OSH Co-ordinator. The contract was realized during the period of March to October 2012.

More photos
Kindergarten, Kolín

A reduction of the energy demands of Masaryk Kindergarten in the town of Kolín. ABP realized the execution of Technical Investor Supervision, and the work of the OSH Co-ordinator. The contract was realized in the year 2013.

More photos
Primary school, Kolín

A reduction of the energy demands of Bezručova Primary School in the town of Kolín. ABP realized the execution of Technical Investor Supervision, and the work of the OSH Co-ordinator. The contract was realized in the year 2013.

More photos
Kindergarten, Prague 13

Reconstruction and insulation of Husníkova Kindergarten in Prague 13. ABP arranged the execution of Technical Investor Supervision, and the work of the OSH Co-ordinator. The contract was realized in the year 2013

More photos
Junction. Prague 9

Construction of a 4-shoulder junction, SSZ 9.213 Poděbradská – Podkovářská, in Prague 9. ABP arranged engineering, relevant permits, the execution of Technical Investor Supervision and the work of the OSH Co-ordinator. The contract was realized in the year 2012.

More photos
Apartment buildings, Mongolia

Construction of 2,000 apartments in the town of Erdenet. In the summer of 2013, ABP and leading development company FINEP commenced the construction of a pilot project – the new residential district “Euro Eko Tugul” in Erdenet, in which a total of 2,000 new modern apartments will gradually be built. The first phase of the construction comprised 2 apartment buildings with a total of 126 apartments, which was realized during the period of May 2013 to December 2014. The total area of all phases of the project is 44 hectares.The second phase was completed in December 2015. The third phase will be completed in December 2016, and the fourth phase has already commenced.

More photos
Business Plan: Meat Processing Factory, Mongolia

ABP, together with its business partners, FINEP HOLDING, SE and Mr. Michal Patek, have been considering building and operating the highest quality meat processing factory in Mongolia. The Czech Development Agency helped to examine the market conditions and to develop a business plan. The Meat factory project has not yet been implemented due to unfavorable financing conditions in Mongolia.
 
Bussiness plan

More photos
Production hall, Mongolia

Complete reconstruction of a production hall, and supply of technology for the manufacture of sandwich panels and nailed wooden tie beams. The ABP team arranged construction work, engineering activity and the financing of the project. The project was realized during the period of May 2006 to March 2007.

More photos